Maintenance (Work Order) Flow Chart Follow
All Work Orders are created in Propertyware
Three Swim Lanes:
1. Tenant calls in. CSR or PM creates WO
2. Tenant creates WO via Westward360 Portal
3. PM Creates WO
- ZD ticket populated in Pre-dispatch queue.
- Set up ticket with CC, subject line & public acknowledgement within 4 business hours.
- Is this a Work Order?
- If NO: ❌
- Apply PM Input Needed macro and assign to PM as OPEN.
- If YES: ✅
- Does dispatch handle this type of WO?
- If yes, review building notes, building issue or unit issue.
- If NO: ❌
UNIT: Apply Troubleshooting Macro(s).
BUILDING: Apply PM Input Needed macro and assign to PM as OPEN.
SINGLE UNIT: Apply PM Input Needed macro and assign to PM as OPEN.
Is Work Order a P1?
- If NO: ❌
- Pend ticket for 3-day follow up (macro).
- Did tenant respond?
- (No) Close WO in PW and ZD ticket solved.
- (Yes) Is building on retainer?
-
(Yes) Pros/Paul Persa or TP (third party)?
- (If TP) Apply PM Input needed macro and assign to PM as OPEN for scheduling.
- (If Pros/Paul Persa) Apply Send to Macro to move ticket to scheduling.
- If YES: ✅
- Chat coordinator with ZD # in Dispatch Escalations Channel (google chat).
- Apply "Send to..." macro to move ticket to scheduling.
PROS, PC or RETAINER?
- PC (project coordinator)
- Work order is scheduled in HCP with text confirmation for PC Vendor.
- Tenant updated via ZD
- Ticket set to pend with due date for next business day after visit.
- Invoice received in Payables queue.
- PROS
- P1?
- If YES: ✅
- Work order is scheduled in HCP for same day.
- Apply "Pros in Progress" macro with next business day after service as due date.
- HCP is reviewed, notes added to ZD
- If NO: ❌
- Is the property under a RETAINER?
-
(Yes)
- Work order is scheduled for next retainer day at building pending availability.
- Apply "Pros in Progress" macro with next business day after service as due date.
- HCP is reviewed, notes added to ZD.
-
(No)
- Is Work order expected to exceed spending limit?
-
(Yes)
- Apply "PM Input Needed" macro and assign to PM as OPEN.
- PM approves.
- Work order is scheduled for 5-days out OR with other WOs at the same building.
- Apply "Pros in Progress" macro with next business day after service as due date.
- HCP is reviewed, notes added to ZD.
-
(No)
- Work order is scheduled for 5-days out OR with other WOs at the same building.
- Apply "Pros In Progress" macro with next business day after service as due date.
- HCP is reviewed, notes added to ZD.
-
(Yes)
- Is the property under a RETAINER?
- If YES: ✅
- P1?
Was Work Order Completed?
- If YES: ✅
- Macro applied, ticket sent for Invoicing as OPEN
- WO is invoiced in HCP, WO closed in PW and ticket submitted as SOLVED.
- If NO: ❌
- "Send to" macro applied to move WO to scheduling.
- Follow back to PROS, PC or Retainer procedure.